Total progress of Melamchi tunnel

This is the total progress of Melamchi tunnel till the last date of my office i.e, yesterday 13th Bhadra, 29th August.

Total Progress Till yesterday: 23,975.80 m; Remaining Length: 1937.40 m.

I had joined this ministry on 18th Kartik 2073, that day the tunnel to be excavated was about 9 km and now its only 1.9 km left to open, Out of total a little more 27 km of tunnel, more than 7 km excavated during my tenure only in the ministry.

This progress update is now the last of my postings on Melamchi in the capacity of secretary of the ministry.

Future updates ,if any, by me will be in the capacity of a common citizen.

Future updates ,if any, by me will be in the capacity of a common citizen.

I would like to thank you all for a good understanding & cooperation for my role in the capacity of Chairperson of the Melamchi Water Supply Development Board and Secretary of the water supply ministry.